• Referendum Projects by Category 
    Below is a list that breaks out by category the type of projects in the $166 million referendum.

    Detailed List of Referendum Projects and Estimated Costs  
    The detailed, itemized list of projects and cost estimates is located at the bottom of this page. 

  • Safety and Security
    Central — $3 million
    South — $2.7 million
    Total — $5.7 million

    Accessibility
    Central — $2.7 million
    South — $2.7 million
    Total — $5.4 million

    Pre-Engineering/STEM 
    Central — $2.1 million
    South — $6.6 million
    Total — $8.7 million

    Infrastructure
    Central — $20 million
    South — $14.4 million
    Total — $34.4 million

    Special Ed/Student Services
    Central — $15.3 million
    South — $8.9 million
    Total — $24.2 million

    Cafeteria
    Central — $4.5 million
    South — $3.4 million
    Total — $7.9 million 

  • Library
    Central — $1.7 million
    South — $4.5 million
    Total — $6.2 million

    Renovate Classrooms
    Central — $2.6 million
    South — $1.6 million
    Total — $4.1 million

    Pool
    Central — $24 million
    South — $15 million
    Total — $39 million

    Space Conversion
    Central — $11.2 million
    Total — $11.2 million


    Fine and Performing Arts
    Central — $14.4 million
    South — $5.1 million
    Total — $19.5 million

    Grand Total
    Central — $101.5 million
    South — $64.7 million
    Total — $166.4 million